Full Text Transcript
Text below was recognized via OCR from scanned pages and may contain minor errors. Mathematical formulas and symbols may be approximate - please refer to the PDF for the exact equations.
1£.S/1.S.S. Examination, 2024 SGSE-G-STS
STATISTICS
Paper - IV
Time Allowed : Three Hours Maximum Marks : 200
Question Paper Specific Instructions
Please read each of the following instructions carefully before attempting
questions :
There are FOURTEEN questions divided under SEVEN Sections.
Candidate has to choose any TWO Sections and attempt the questions therein. All the
Sections carry equal marks.
The number of marks carried by a question / part is indicated against it.
Wherever any assumptions are made for answering a question, they must be clearly
indicated.
Diagrams/ Figures, wherever required, shall be drawn in the space provided for answering
the question itself.
Unless otherwise mentioned, symbols and notations have their usual standard meanings.
Attempts of questions shall be counted in sequential order. Unless struck off, attempt of a
question shall be counted even if attempted partly.
Any page or portion of the page left blank in the Question-cum-Answer Booklet must be
clearly struck off.
Answers must be written in ENGLISH only.
SGSE-G-STS 1
Ql. (a)
(b)
(c)
SGSE-G-STS
SECTION A
(Operations Research and Reliability)
An electronics company manufactures two types of LEDs (Model 1 and
Model 2). The daily capacity of the company is 60 LEDs of Model 1 and
75 LEDs of Model 2. Each model of the first type uses 10 pieces of an
electronic component whereas a model of second type uses 8 pieces of
this component. The maximum availability of this component is 800
pieces. The company is committed to manufacture at least 20 pieces of
Model 2 per day. If the net profit on the sale of these two models is = 40
and = 30 respectively, then determine the production schedule which
maximizes the profit of the company. (Graph paper is attached)
Define saddle point of a game problem. Use the Principle of Dominance
to find the optimal strategies of the two players with the following payoff
matrix :
Player B
Dal SH EV.
HS eb oA oo
Te 62 224
Sue Oa 1 ko
IVES 53 2 Do
Use Vogel’s Approximation Method to find feasible solution to the
following transportation problem :
Destinations
D; Dz Dg _ Dg | Supply
22 eS
Origins
O5 |-10'- 8 5 4 7
O37). 7 6 6 8 5
Requirement 4 3 4 4
10
10
10
(d)
(e)
Let (x) be a coherent structure of n components. Show that, under
usual notations,
o(x Ly) = o(x) LL oy).
What is the application of this principle among engineers ? 10
A non-negative random variable T has cumulative distribution function
F(t) given by :
8 1
F(t)=1--et+ =e t>0
(t) 7° 7
Find the hazard rate and mean time to failure. 10
Q2. Answer any two from the following :
(a)
SGSE-G-STS
(i) We have five jobs A, B, C, D and E. Each of these jobs must go
through three machines Mj, Mz and Mg for processing in the
order M,Mp2Msz. Processing time (in hours) are given below :
Processing Time (in hours)
Jobs My M2 M3
A 4 5 8
B 9 6 10
Cc 8 2 6
D 6 3 7
E 5 4 abl
Determine an optimal sequence of jobs that will minimize the
total elapsed time. Also, calculate the idle times of the three
machines. 20
(ii) | Explain Hungarian Method for finding optimal solution to an
Assignment Problem. 5
(b)
(c)
(d)
SGSE-G-STS
(i)
(ii)
Consider the following project :
Activity Time (in days)
(1, 2) 4
(1, 3) 3
(2, 4) 6
(3, 5) 5
(4, 5) 7
(4, 6) 9
(5, 7) 8
Find the critical path and duration of completion of the above
project.
An industry needs 5400 units/year of a bought out component
which will be used in its main product. The ordering cost is € 250
per order and carrying cost per unit/year is = 30. Find the
Economic Order Quantity (EOQ), the number of orders/year and
the time between successive orders.
Let T denote the random variable having Weibull distribution with edf
F(t) given by :
i)
(ii)
(i)
F(t) =1-e™™, t,0,0>0.
Discuss the monotonicity of the hazard rate.
Describe the procedure for finding the MLEs of its parameters, by
constructing the likelihood function, using a time censored
sample.
Show that the hazard rate of a series system of n independent
components is the sum of its component hazard rates. Hence,
show that if all components have IFR, then the series system is
also of the IFR type.
15
10
10
15
15
SGSE-G-STS
(ii)
Consider the following linear programming problem :
Maximize Z = 2x1 + 3x9 +
subject to
+ + < 1 (labour)
ବକ୍ଷ + 352 + ix < 3 (material)
X1, 29) 20
with optimal table as
0 2 3 1 0 0
b b 2 31 XQ X4 X5
2 Xy “0. 54: |: 1 |
3 Xp 0 દ हिया 55
9/0 0 9.4. 22
Determine, how far the availability of labour can be varied such
that the optimal table remains optimal.
10
SECTION B
(Demography and Vital Statistics)
Q3. (a) Define the force of mortality at exact age x. Derive its formula. If
U(x) = 100 ./100 — x, using an appropriate method find (84). 10
(b) Discuss various types of migration. Explain Vital Statistical Method of
obtaining Net Migration (NM). 10
(c) Define Stable and Stationary population. Discuss their properties. Write
the importance of the Stable Population theory in the study of Vital
Statistics. 10
(d) Write the salient features of Indian Census 2011. Also mention the
importance of preparing census. 10
(e) Explain Gompertz’s law for mortality, and derive the formula for the
law. Also write its applications. 10
Q4. Answer any two from the following :
(a) Discuss the different measures of mortality with their relative merits
and demerits. 25
(b) Define life table and write its importance in the study of Vital Statistics
in detail. Discuss various measures of life table functions. 25
(ec) Define Age Specific Fertility Rate. Write its importance in Vital
Statistics. For the following data, calculate ASFR. For which age group
is ASFR the highest ? Is a fertility curve of ASFR against age positively
skewed ?
Age of Number of Number of
Mother live births | females (000)
15-19 23,604 5,467
20 — 24 4,01,080 4,520
25 — 29 9,48,848 4,371
80 — 34 3,84,315 4,210
35 — 39 77,871 3,899
40 — 44 9,489 3,460
45 — 49 435 2,850
Also calculate GFR and GRR when the proportion of female births is
46:5 percent. 25
(d) Explain the method due to Rhodes for fitting of Logistic curve for
population projection. Illustrate how you would fit a logistic curve to the
given data set using this method. 25
SGSE-G-STS 6
Q5. (a)
(b)
(c)
(d)
(e)
SECTION C
(Survival Analysis and Clinical Trials)
Define time, order and random censoring schemes. Give an example of
each.
The following data relates to survival times of patients after a surgery.
(+ denotes right censored observations)
Male : 6+, 11, 18+, 15, 216+
Female: 2+, 4, a5 8+
A Cox proportional model A(t, x) = Ag(t)e®* is to be fitted to these data;
where
Ao(t) is baseline hazard
x= 0if male
= 1if female
t is the surviving time after surgery
Construct Cox partial likelihood for the data.
Explain competing risks model in survival analysis.
Distinguish between controlled and uncontrolled clinical trials.
Describe multicenter trials in clinical trials.
Q6. Answer any two from the following :
(a)
(b)
(c)
(d)
SGSE-G-STS
Describe Gamma distribution as a failure time model in survival
analysis. Explain why this distribution is less popular compared to
Weibull distribution. Write down the likelihood in the order censored
sample.
In a study, 30 patients are observed for two years following treatment
with a new drug. The following data shows the period t in complete
months from the initial treatment to the end of the observation for those
patients who died or withdrew from the trial before the end of the two
year period.
Deaths : 6, 6; 12; 4.15, -20;.205 25;
Withdrawals: 1, 3, 5, 8, 1037: 18:
(i) Calculate Kaplan-Meier estimate St) of S(t).
Gi) Calculate V(8(t)) at t = 14.
Describe the ethics, objectives and protocols to be followed in conducting
the clinical trials.
(i) Describe data collection system in clinical trials.
(ii) | Explain parallel and cross-over designs in clinical trials.
vA
10
10
10
10
10
25
15
10
25
10
15
Q7. (a)
(b)
(c)
(d)
SGSE-G-STS
Distinguish between process control and product control. Also explain
how the chance causes and assignable causes affect both.
The following data gives the number of 10 independent samples of
SECTION D
(Quality Control)
varying size from a production process :
Rample Sample size Number of
number defectives
1 2000 425
2 1500 430
3 1400 216
4 1350 341
5 1250 225
6 1760 322
© 1875 280
8 1955 306
9 3125 337
10 1575 305
Draw the control chart for fraction defective and comment on it.
(A graph paper is provided to draw the chart)
Discuss the use and importance of control chart for number of defects
per unit. Suppose a manufacturing process results in 2% defects per
unit. Obtain the control limits for c-chart if 500 units are sampled.
Explain the procedure of a single sampling inspection plan and obtain
its operating characteristic function. Suppose large batches of screws are
subjected to a single sampling plan with n = 60 and c = 2. If the process
average is p = 0-01, does this lot accept batch of high quality with high
probability ?
10
10
10
10
(e)
Explain the following terms with respect to sampling inspection plans :
(i) Acceptance Quality Level (AQL)
(ii) | Lot Tolerance Percent Defective (LTPD)
(ii) Average Outgoing Quality Limit (AOQL)
(iv) Operating Characteristic Curve
(v) | Consumer’s Risk
Q8. Answer any two from the following :
(a)
SGSE-G-STS
The following data were collected from a process manufacturing power
supplies company. The variable of interest is output voltage and n = 5.
ee ee Oe ee
a 103 4 11 105 o
2 102 5 12 103 2
3 104 2 13 102 3
4 105 8 14 105 4
5 104 4 15 104 5
6 106 3 16 105 3
7 102 tf 17 106 5
8 105 2 18 102 2
9 106 4 19 105 4
10 104 3 20 103 2
(i) Compute center line and control limits for controlling future
production. (Use x -chart and R-chart)
(ii) | Assuming that the quality characteristic is normally distributed,
estimate the process standard deviation.
(iii) What are the natural tolerance limits of the process ?
(iv) Estimate the process fraction non-conforming if the specifications
were 103 + 4.
(v) | Obtain the capability (both C, and C,),) of the process.
(Given for n = 5, Ag = 0:58, D3 = 0, D4 = 2-115, dg = 2°326)
9
10
25
(b)
(c)
(d)
SGSE-G-STS
Explain the utility and applications of Cumulative Sum (CUSUM) chart.
A machine produces spokes for the wheels of bicycles. When the process
is in control, the machine produces spokes whose lengths are normally
distributed about mean 25 cm and standard deviation 0-02 cm. The
sample values are given as follows :
24-998 25-016 25-024 25022 24-984
25-012 25-024 24:978 25012 25:017
25-024 25-026 25-027 25:028 25-028
Use CUSUM chart to investigate whether the machine is correctly set.
Also investigate at what point the linearity is observed and provide the
corresponding estimate. Plot the chart in the graph paper provided.
What is Acceptance Sampling Plan ? In usual notation, explain the
procedure of Double Sampling Plan. Also state how it differs from
sequential sampling plan.
The following data represents individual observations on molecular
weight taken hourly from a chemical process :
1045 1055 1037 1064 1095 1008 1050
1087 1125 1146 1139 1169 1151 1128
1238 1125 1163 1188 1146 1167
The target value of molecular weight is 1050 and the process standard
deviation is thought to be about 25. Use an Exponentially Weighted
Moving Average (EWMA) chart with A = 0-2 and L = 2:7 and analyse the
data. A manual chart may be prepared to show the steady-state position.
10
25
25
25
Q9. (a)
(b)
()
SGSE-G-STS
SECTION E
(Multivariate Analysis)
Energy consumption in 2001, by State, from the major sources
2] - petroleum
22 = natural gas
= hydroelectric power
x4 = nuclear electric power
is recorded in quadrillions (1015) of BTUs.
The resulting mean and covariance matrix are :
0766 0-856 0-685 0-173 0-096
_ 10508 0-635 0-568 0-128 0-067
± = | 0.438 |° ` [0178 0-127 0-171 0-039
0161 0-096 0-067 0-039 0-048
Using the summary statistics, determine the sample mean and variance
of the State’s total energy consumption for these major sources when
x: 4x 1 15 distributed as 4404, ). 10
Let x,, r = 1, 2, ..., k be independently identically distributed as
N,(u, 2). For fixed matrices A, : mx p, r = 1, 2, ..., k, obtain the
distribution of
k
.
r=]
Using the distribution you have obtained, derive the distribution of the
sample mean vector . 10
Let x ~ Na(u, 2.) where p’ = (1, - 1, 1) and
3 1
| 61,
1 ತ್ತಿ
Obtain the joint distribution 0877] = 221 + 2x9 - 333 and
2 = 21 ¬ 22 + 3x3. Obtain the correlation coefficient between 71 and yp.
Are they positively correlated ? 10
11
(d)
(e)
Define Wishart matrix and Wishart distribution. If , x2 and x3 are
independent observations from 171, 3) population with = 0 and
1.2
9], then
; te E / / ^
(i) compute E(x,x + ± ® + ± 5X5)
se BE 1 1
(1) compute (| ± ® + XxX) + X5X |)
(iii) mention the distribution of (x) x} + XoXo + 3 10
Define canonical correlations and variates. State the condition when
(i) multiple correlation coefficient, and (ii) simple correlation coefficient
can be obtained as a particular case of canonical correlations.
In usual notations, show that, if A; is an eigenvalue of
9.
11 12 22 21 11
with associated eigenvector e;, then A; is also an eigenvalue of
1 7 ಇತ್ತ
Zi, 12
1
with eigenvector 22 . 70
11
Q10. Answer any two from the following :
(a)
SGSE-G-STS
Consider the data matrix
-1 3 -2
X=| 2 4 21.
5 2 3
(i) Calculate the matrix of deviations (residuals), X - 1x’. Is this
matrix of full rank ? Explain.
(ii) | Determine 5 and calculate the generalised sample variance |5|.
Gii) Using the result in (ii), calculate the total sample variance.
(iv) Obtain the distribution of generalised variance. 25
72
(b)
(c)
SGSE-G-STS
Determine the population principal components and for the
covariance matrix
9 -2
> 0 |
Also calculate the proportion of the total population variance explained
by the first principal component. Convert the covariance matrix 2) into a
correlation matrix p. Determine the principal components Y; and 2
from p and compute the total population variance explained by 7.
Compare the components calculated using 2. and 0. Are they same ?
Should they be ?
Test the null hypothesis Hg : = against an alternative hypothesis
Hy : × when x - Np(u, ).
Let the data matrix for a random sample of size n = 3 from a bivariate
normal population be
4 1
X=/-1 3
306
(i) Evaluate 72, for testing Ho : 11 = (3; 2):
(ii) 5005 the distribution of T? evaluated in (i).
(iii) Test Ho at the © = 0-05 level of significance.
Write your conclusion.
( 1 (0-05) = 200, , 1 (0-01) = 4999, Fo, 2 (0-05) = 19-00
)99-17 = )0-01( Fs, ,19-16 = )0-05( ,9-55 = )0-05( 3 7
13
25
25
(d)
SGSE-G-STS
Obtain a classification rule for classifying an individual xp into one
of the two populations [Ij and [lg such that Expected Cost of
Misclassification (ECM) is minimum.
Suppose that the density functions evaluated at a new observation
Xo give f}(xo) = 0°35 and fo(xo) = 0-45, where f;(x) and fo(x) are density
functions associated with populations Il, and Ig. If c(1/2)=80 and
c(2/1) = 40 units and it is known that about 30% of all objects belong to
population Ip, then classify xp using minimum ECM rule.
14
25
Ql1l1. (a)
(b)
(c)
(d)
(e)
SGSE-G-STS
SECTION F
(Design and Analysis of Experiments)
Discuss the Gauss-Markov linear model stating all assumptions
underlying there. Also discuss how a general effect model and random
effect model can be perceived as a particular case of Gauss-Markov
model. 10
32 plots are arranged in the form of a 4 x 8 rectangle. Suppose a 2°
design with factors A, B, C, D and E at two-levels each is considered,
where the effects ABC, CDE, ABDE are confounded in rows and AB, CD,
ABCD, BDE, ADE, BCE, ACE with the columns. Suggest a confounded
design arrangement for the above experiment. 10
A 2? factorial experiment was conducted to determine whether the type
of glass and phosphor type affected the brightness of a television tube.
The following table presents three response measures each of the
current necessary (in micro-amps) to obtain a specified brightness level.
Measurement of current (in micro-amps)
Phosphor Type
Glass Type
A B
dl 280 300
290 310
285 295
2 230 260
235 240
240 235
Analyse the design and conclude at a = 5%.
[Given 5 Fi, 5 be 5°32, Fp, el 4-46
Fig, 8] = 4:07, Fi4, 9] = 3°84] 10
What are the advantages and disadvantages of split-plot design ? Also
state the practical use of such a design. 10
Explain strip-plot design and its features. 10
15
Q12. Answer any two from the following :
(a)
(b)
(c)
SGSE-G-STS
An analysis of covariance (ANCOVA) for an RBD with ‘b’ blocks and ‘Vv
treatments observed on an auxiliary variable ‘x’ related to the main
variable ‘y’ is given as
Yj =H + Bi + Fj + Vay + Cy
jog. ok
ed Zo ew
where y;;(x;j) is the yield of treatment j in block i and e;; ~ N(O, o2). The
other parameters have usual meaning. Now investigate the following :
(i) Estimate the parameters : (u; Bj, 7), Y)
Gi) Test Hp: 1, ==... =7, against
Hy, : not all are equal, but at least one inequality is strict
(iii) Unbiased estimate of 0?
(iv) ANCOVA table for RBD 25
Consider the following model :
Yij =U + 04 + Bj + Vij, .
lee
Jel, 2535.0
where aj, B; satisfy the condition >) a,= Laps B = 0, and )j; is a random
i j
component with E(%;;) = 0, ED; = 3, Prepare the ANOVA table for
analysing the design and suggest the expected sum of squares due to all
sources of variation. 25
An online taxi company wants to consider four types of cars (Say : A, B,
C, D) for its efficient management of realizing customer demands. This
is tested using four car drivers on four different routes. The efficiency of
cars is measured in terms of minutes to complete a particular distance.
The layout and time consumed by each vehicle for each driver on each
route are given below :
16
Time taken to cover a particular distance
Drivers
Route
1 2 3 4
1 18(C) 12(D) 16(A) 20(B)
2 26(D) 34(A) 25(B) 31(C)
3 15(B) 22(C) 10(D) 28(A)
4 830(A) 20(B) 15(C) 9(D)
Analyze the design and conclude for « = 0-05 level of significance.
[Given F(g ¢) = 4°76
F(4,6) = 453 7 for = 0-05
Fo, 6) = 4°39 25
(d) In usual notations, obtain
(i) the efficiency of RBD with respect to CRD. 10
(ii) the efficiency of LSD with respect to RBD. 15
where
CRD : Completely Randomized Design
RBD : Randomized Block Design
LSD : Latin Square Design
SGSE-G-STS LT,
Q13. (a)
(b)
(c)
(d)
(e)
SECTION G
(Computing with C and R)
Why do we use Relational and Logical Operators in C ? List them with
their syntaxes.
Write a C-program to compute median for grouped data.
Write a program in C to calculate Coefficient of Variation for a set of n
observations.
Write R codes to fit a Binomial distribution to the following data :
x 0 1 2 3 4 5 6 7
f 7 6 19 35 30 23 7
Heights (in cm) of 8 randomly selected students from normal population
with a standard deviation of 5 are given below :
168, 170, 185, 172, 169, 158, 170, 175
Write R-codes for performing Z-test for testing population mean height
value of 140 cm at a = 0:05.
Q14. Answer any two from the following :
(a)
(b)
(c)
(d)
SGSE-G-STS
Describe control statements in C with the help of an example in each
case.
Write a C-program to obtain ANOVA table for a Randomized Block
Design (RBD) having t-treatments in r-blocks.
Write a C-program to compute regression equation of Y on X for a given
data set.
How do we read matrices in R ? Write R-codes for performing the
following matrix operations : addition, multiplication, transposing,
determinant and finding the inverse of a matrix.
18
10
10
10
10
10
25
25
25
25
P(O < Z < 1.96) = 0.4750
The Normal Distribution
Z 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09
0.0 | 0.0000 0.0040 0.0080 0.0120 0.0160 0.0199 0.0239 0.0279 0.0319 0.0359
0.1 | 0.0398 0.0438 0.0478 0.0517 0.0557 0.0596 0.0636 0.0675 0.0714 0.0753
0.2 | 0.0793 0.0832 0.0871 0.0910 0.0948 0.0987 0.1026 0.1064 0.1103 0.1141
0.3 | 0.1179 0.1217 0.1255 0.1293 0.1331 0.1368 0.1406 0.1443 0.1480 0.1517
0.4 | 0.1554 0.1591 0.1628 0.1664 0.1700 0.1736 0.1772 0.1808 0.1844 0.1879
0.5 | 0.1915 0.1950 0.1985 0.2019 0.2054 0.2088 0.2123 0.2157 0.2190 0.2224
0.6 | 0.2257 0.2291 0.2324 0.2357 0.2389 0.2422 0.2454 0.2486 0.2517 0.2549
0.7 | 0.2580 0.2611 0.2642 0.2673 0.2704 0.2734 0.2764 0.2794 0.2823 0.2852
0.8 | 0.2881 0.2910 0.2939 0.2967 0.2995 0.3023 0.3051 0.3078 0.3106 0.3133
0.9 | 0.3159 0.3186 0.3212 0.3238 0.3264 0.3289 0.3315 0.3340 0.3365 0.3389
1.0 | 0.3413 0.3438 0.3461 0.3485 0.3508 0.3531 0.3554 0.3577 0.3599 0.3621
1.1 | 0.3643 0.3665 0.3686 0.3708 0.3729 0.3749 0.3770 0.3790 0.3810 0.3830
1.2 | 0.3849 0.3869 0.3888 0.3907 0.3925 0.3944 0.3962 0.3980 0.3997 0.4015
1.3 | 0.4032 0.4049 0.4066 0.4082 0.4099 0.4115 0.4131 0.4147 0.4162 0.4177
14 | 0.4192 0.4207 0.4222 0.4236 0.4251 0.4265 0.4279 0.4292 0.4306 0.4319
1.5 | 0.4332 0.4345 0.4357 0.4370 0.4382 0.4394 0.4406 0.4418 0.4429 0.4441
1.6 | 0.4452 0.4463 0.4474 0.4484 0.4495 0.4505 0.4515 0.4525 + 0.4535~—«(0.4545
1.7 | 0.4554 0.4564 0.4573 0.4582 0.4591 0.4599 0.4608 0.4616 0.4625 0.4633
18 | 0.4641 0.4649 0.4656 0.4664 0.4671 0.4678 0.4686 0.4693 0.4699 0.4706
1.9 | 0.4713 0.4719 0.4726 0.4732 0.4738 0.4744 0.4750 0.4756 0.4761 «0.4767
2.0 | 0.4772 0.4778 0.4783 0.4788 0.4793 0.4798 0.4803 0.4808 0.4812 0.4817
2.1 | 0.4821 0.4826 0.4830 0.4834 0.4838 0.4842 0.4846 0.4850 0.4854 0.4857
2.2 | 0.4861 0.4864 0.4868 0.4871 0.4875 0.4878 0.4881 0.4884 0.4887 _0.4890
2.3 | 0.4893 0.4896 0.4898 0.4901 0.4904 0.4906 0.4909 0.4911 0.4913 0.4916
24 | 0.4918 0.4920 0.4922 0.4925 0.4927 0.4929 0.4931 0.4932 0.4934 0.4936
2.5 | 0.4938 0.4940 0.4941 0.4943 0.4945 0.4946 0.4948 0.4949 0.4951 0.4952
2.6 | 0.4953 0.4955 0.4956 0.4957 0.4959 0.4960 0.4961 0.4962 0.4963 0.4964
2.7 | 0.4965 0.4966 0.4967 0.4968 0.4969 0.4970 0.4971 0.4972 0.4973 0.4974
2.8 | 0.4974 0.4975 0.4976 0.4977 0.4977 0.4978 0.4979 0.4979 0.4980 0.4981
2.9 | 0.4981 0.4982 0.4982 0.4983 0.4984 0.4984 0.4985 0.4985 0.4986 0.4986
3.0 | 0.4987 0.4987 0.4987 0.4988 0.4988 0.4989 0.4989 0.4989 0.4990 0.4990
3.1 | 0.4990 0.4991 0.4991 0.4991 0.4992 0.4992 0.4992 0.4992 0.4993 0.4993
3.2 | 0.4993 0.4993 0.4994 0.4994 0.4994 0.4994 0.4994 0.4995 0.4995 0.4995
3.3 | 0.4995 0.4995 0.4995 0.4996 0.4996 0.4996 0.4996 0.4996 0.4996 0.4997
3.4 | 0.4997 0.4997 0.4997 0.4997 0.4997 0.4997 0.4997 0.4997 0.4997 0.4998
3.5 | 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998 0.4998
3.6 | 0.4998 0.4998 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999
3.7 | 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999
3.8 | 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999 0.4999
3.9 | 0.5000 0.5000 0.5000 —-0.5000~—S0.5000 —_—0.5000 ~—0.5000 ~—0.5000 ~—0.5000 ~—_—0.5000
SGSE-G-STS 19